HOBOKEN — According to the agenda for the Wednesday City Council meeting, the company managing the Washington Street Redesign project has requested a 29-day time extension, which will be discussed during the meeting at 7 p.m.
T&M Associates had already received a time extension, which gave them a deadline of Aug. 21. The second extension would aim for the completion of the project on Sept. 21.
In a letter to the city included in the council documents, T&M Associates writes that they may need an additional 147 days to complete the project.
“At the request of city administration, our office evaluated the remaining contract work to be completed against the rate of production of work completed to date and it is evident even the revised completion date of September 21, 2018, may not be sufficient… with six (6) intersections remaining to complete drainage, rain garden, curb extension, ADA compliant ramps, traffic signal, microgrid conduit, milling, paving, signage and striping installation, our office projects an additional 3.5 weeks per intersection, or additional 147 days, may be needed beyond the time approved within this change order.”
Hoboken’s Washington Street Redesign may now be finished at end of September
Bayonne
broken clouds
44.4
°
F
48.3
°
41
°
46 %
2.9mph
75 %
Sun
43
°
Mon
44
°
Tue
42
°
Wed
50
°
Thu
54
°
Upcoming Events
Shamanic Sound Journey
• 02/07/2023 at 7:30 pm - 9:00 pm
Shamanic Sound Journey
• 02/10/2023 at 7:30 pm - 9:00 pm
Energy Medicine Yoga
• 02/11/2023 at 2:00 pm - 3:30 pm
Grupo Niche
• 02/11/2023 at 8:00 pm - 11:00 pm
Sound Bath Energy Healing
• 02/13/2023 at 7:30 pm - 9:30 pm
• 02/07/2023 at 7:30 pm - 9:00 pm
Shamanic Sound Journey
• 02/10/2023 at 7:30 pm - 9:00 pm
Energy Medicine Yoga
• 02/11/2023 at 2:00 pm - 3:30 pm
Grupo Niche
• 02/11/2023 at 8:00 pm - 11:00 pm
Sound Bath Energy Healing
• 02/13/2023 at 7:30 pm - 9:30 pm